‘DCK Gateway District’ Latest Progress Update – September 2013


Here is the latest update of ‘DCK Gateway District‘. DHA City Karachi is the First Planned, Sustainable & Green City of Pakistan. What’s your views about the DCK Development Speed? Let us know via comments. Thanks!

DCK Gateway District will consist of:

  • DCK Directorate Office
  • Central Facility Building
  • Visitors Centre
  • Staff Accommodation
  • Officers Apartments
  • Masjid
  • DHA Office
  • Cantonment Office

If you are looking to buy or sell plots in DHA City Karachi,
then contact CITI Associates at 0321-8793654 or email at citiassociates.dck@gmail.com

You may also like to checkout:

Note: Click on the image to view the higher resolution version

'DCK Gateway District' Latest Progress Update - September 2013 (1) 'DCK Gateway District' Latest Progress Update - September 2013 (2) 'DCK Gateway District' Latest Progress Update - September 2013 (3) 'DCK Gateway District' Latest Progress Update - September 2013 (4) 'DCK Gateway District' Latest Progress Update - September 2013 (5) 'DCK Gateway District' Latest Progress Update - September 2013 (6) 'DCK Gateway District' Latest Progress Update - September 2013 (7) 'DCK Gateway District' Latest Progress Update - September 2013 (8) 'DCK Gateway District' Latest Progress Update - September 2013 (9) 'DCK Gateway District' Latest Progress Update - September 2013 (10) 'DCK Gateway District' Latest Progress Update - September 2013 (11) 'DCK Gateway District' Latest Progress Update - September 2013 (12) 'DCK Gateway District' Latest Progress Update - September 2013 (13) 'DCK Gateway District' Latest Progress Update - September 2013 (14) 'DCK Gateway District' Latest Progress Update - September 2013 (15) 'DCK Gateway District' Latest Progress Update - September 2013 (16) 'DCK Gateway District' Latest Progress Update - September 2013 (17) 'DCK Gateway District' Latest Progress Update - September 2013 (18) 'DCK Gateway District' Latest Progress Update - September 2013 (19) 'DCK Gateway District' Latest Progress Update - September 2013 (20) 'DCK Gateway District' Latest Progress Update - September 2013 (21) 'DCK Gateway District' Latest Progress Update - September 2013 (22) 'DCK Gateway District' Latest Progress Update - September 2013 (23) 'DCK Gateway District' Latest Progress Update - September 2013 (24) 'DCK Gateway District' Latest Progress Update - September 2013 (25) 'DCK Gateway District' Latest Progress Update - September 2013 (26) 'DCK Gateway District' Latest Progress Update - September 2013 (27) 'DCK Gateway District' Latest Progress Update - September 2013 (28) 'DCK Gateway District' Latest Progress Update - September 2013 (29) 'DCK Gateway District' Latest Progress Update - September 2013 (30) 'DCK Gateway District' Latest Progress Update - September 2013 (31) 'DCK Gateway District' Latest Progress Update - September 2013 (32) 'DCK Gateway District' Latest Progress Update - September 2013 (33) 'DCK Gateway District' Latest Progress Update - September 2013 (34) 'DCK Gateway District' Latest Progress Update - September 2013 (35) 'DCK Gateway District' Latest Progress Update - September 2013 (36) 'DCK Gateway District' Latest Progress Update - September 2013 (37) 'DCK Gateway District' Latest Progress Update - September 2013 (38) 'DCK Gateway District' Latest Progress Update - September 2013 (39) 'DCK Gateway District' Latest Progress Update - September 2013 (40) 'DCK Gateway District' Latest Progress Update - September 2013 (41) 'DCK Gateway District' Latest Progress Update - September 2013 (42) 'DCK Gateway District' Latest Progress Update - September 2013 (43) 'DCK Gateway District' Latest Progress Update - September 2013 (44)

Comments (4)

Trackback URL | Comments RSS Feed

  1. Muhammad Wasim says:

    Very Slow Progress, Wake Up guys . I think DHA Administrator need to take action against Consultant and Contractors. Due to this speed DHA will lose its credibility . They have not completed one of them on time still in progress.

    13 Immediate Action Plan Works at DHA City Karachi (DCK)

    Boundary Wall : Date of Completion 2 Feb 2013

    Const of Wath Towers : Date of Completion 2 August 2012

    Const of DCK DTE Office : Date of Completion 9 Feb 2013

    Const of Staff ACCN : Date of Completion 24 Feb 2013

    Const of Single OFFRS ACCN : Date of Completion 12 March 2013

    Const of Central Facility BLD : Date of Completion 14 Mar 2013

    Const of OFFRS Apartments : Date of Completion 16 APR 2013

    Const of Visitors Centre :

    Const of Access Road : Date of Completion 10 May 2012

    Const of Main Entrance

    Const of Lake View Park.

    Water Exploration .

    const of PRE-FAB Officers and ACCN : Date of Completion 30 Apr 2012 , Extended Date : 31 July 2012